Resurfacing - Cawthra Road from Lakeshore Road to North Service Road
Federal contribution
$302,142
Federal share30%
of $997.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedMar 25, 2011
20102011
Built
Approved 22 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Regional Municipality of Peel
- Construction start
- Aug 31, 2009(actual)
- Construction end
- Nov 1, 2009(actual)
Against the original forecast
- Construction start4 weeks lateforecast Aug 1, 2009
- Construction end5 months earlyforecast Mar 31, 2010
Also in Mississauga