Batawa-Frankford Water and Wastewater Development

Frankford, Ontario

completeDrinking WaterISF
Federal contribution
$1.7M
$1,666,667
Federal share33%

of $5.0M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Quinte West
Construction start
Jan 15, 2010(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start3 months earlyforecast Apr 30, 2010
  • Construction end4 weeks lateforecast Sep 30, 2011

Also in Frankford