Federal contribution
$116,666
Federal share33%
of $350.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Township of Strong
- Construction start
- Oct 19, 2009(actual)
- Construction end
- Mar 31, 2011(actual)
Against the original forecast
- Construction start3 weeks lateforecast Oct 1, 2009
- Construction end6 months lateforecast Sep 30, 2010