Silverthorn pumping station improvements and upgrades

Mississauga, Ontario

completeDrinking WaterISF
Federal contribution
$1.1M
$1,067,082
Federal share33%

of $3.3M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Dec 30, 2009(actual)
Construction end
Nov 15, 2010(actual)

Against the original forecast

  • Construction start12 months earlyforecast Dec 30, 2010
  • Construction end4 months earlyforecast Mar 31, 2011

Also in Mississauga

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32196 in the federal list. How to read these figures.