Back to projects

Sand Storage Building

Amaranth, Ontario

completeHighways and RoadsISF
Federal contribution
$86,711
Federal share33%

of $260.1K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Township of Amaranth
Construction start
Jun 30, 2009(actual)
Construction end
Dec 31, 2009(actual)

Against the original forecast

  • Construction start3 months earlyforecast Sep 21, 2009
  • Construction end4 weeks lateforecast Nov 30, 2009

Also in Amaranth

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32237 in the federal list. How to read these figures.