New Library in Greely
Federal contribution
$391,256
Federal share33%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Ottawa
- Construction start
- Jul 2, 2010(actual)
- Construction end
- Mar 2, 2011(actual)
Against the original forecast
- Construction end4 weeks earlyforecast Mar 31, 2011
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32282 in the federal list. How to read these figures.