Reservoir Rehabilitation Project - Silverthorn Reservoir
Federal contribution
$480,784
Federal share32%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Regional Municipality of Peel
- Construction start
- Jan 4, 2010(actual)
- Construction end
- Mar 31, 2011(actual)
Against the original forecast
- Construction start3 months earlyforecast Mar 31, 2010
Also in Mississauga
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32365 in the federal list. How to read these figures.