Thedford Village Green
Federal contribution
$167,899
Federal share33%
of $503.7K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Municipality of Lambton Shores
- Construction start
- Nov 16, 2009(actual)
- Construction end
- May 18, 2010(actual)
Against the original forecast
- Construction end2 months earlyforecast Jul 30, 2010
Also in Thedford
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32373 in the federal list. How to read these figures.