Water Master Plan Implementation - OConnor Drive Reservoir and Discharge Header
Federal contribution
$3.1M
$3,145,429
Federal share26%
of $12.3M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Kingston
- Construction start
- Aug 26, 2009(actual)
- Construction end
- Oct 14, 2011(actual)
Against the original forecast
- Construction end2 weeks earlyforecast Oct 31, 2011
Also in Kingston
- City of Kingston Third Crossing Bridge$60.0M
- Ministry of Transportation Ontario Eastern Region New Ferry Vessels$31.3M
- Kingston Wastewater Treatment Plant Upgrades$25.0M
- Isabel Bader Centre for the Performing Arts at Queen's University at Kingston$15.0M
- Long Range Battery Electric Conventional Transit Buses and Bio- Diesel/Hybrid Buses$12.3M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32408 in the federal list. How to read these figures.