Hagerman Community Centre Renovations

Whitestone, Ontario

completeRecreationISF
Federal contribution
$16,667
Federal share33%

of $50.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Municipality of Whitestone
Construction start
Oct 13, 2009(actual)
Construction end
Dec 15, 2009(actual)

Against the original forecast

  • Construction start7 months earlyforecast May 1, 2010
  • Construction end11 months earlyforecast Oct 31, 2010

Also in Whitestone

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32435 in the federal list. How to read these figures.