Stisted Road Reconstruction

Sprucedale, Ontario

completeHighways and RoadsISF
Federal contribution
$59,377
Federal share31%

of $190.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Jul 15, 2010(actual)
Construction end
Oct 15, 2010(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Jun 30, 2010
  • Construction end2 weeks lateforecast Sep 30, 2010