Prescott Subdivision - Pedestrian and Cyclist Rural Pathway

Osgoode, Ontario

completeHighways and RoadsISF
Federal contribution
$451,847
Federal share33%

of $1.4M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Ottawa
Construction start
Aug 27, 2010(actual)
Construction end
Jun 24, 2011(actual)

Against the original forecast

  • Construction start2 months lateforecast Jun 22, 2010
  • Construction end3 months lateforecast Mar 31, 2011

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32499 in the federal list. How to read these figures.