Renewal of the Mary J.L. Black Library

Thunder Bay, Ontario

completeCultureISF
Federal contribution
$1.4M
$1,370,000
Federal share33%

of $4.1M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Thunder Bay
Construction start
Jun 30, 2010(actual)
Construction end
Jun 30, 2011(actual)

Against the original forecast

  • Construction end2 weeks earlyforecast Jul 15, 2011

Also in Thunder Bay

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32514 in the federal list. How to read these figures.