Upgrade Menzies Munro Road
Federal contribution
$103,071
Federal share32%
of $320.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Township of Tay Valley
- Construction start
- May 17, 2010(actual)
- Construction end
- Jun 30, 2010(actual)
Against the original forecast
- Construction start6 weeks lateforecast Apr 2, 2010
- Construction end3 months earlyforecast Sep 30, 2010
Also in Tay Valley
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32527 in the federal list. How to read these figures.