Queen/Nelson Street reconstruction
Federal contribution
$713,333
Federal share33%
of $2.1M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Town of Petrolia
- Construction start
- Oct 30, 2009(actual)
- Construction end
- Jun 28, 2010(actual)
Against the original forecast
- Construction start4 weeks earlyforecast Nov 30, 2009
- Construction end9 months earlyforecast Mar 31, 2011