Kennedy Drive Rehabilitation

Galway-Cavendish and Harvey, Ontario

completeHighways and RoadsISF
Federal contribution
$101,021
Federal share25%

of $400.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Aug 7, 2009(actual)
Construction end
Oct 31, 2009(actual)

Against the original forecast

  • Construction start2 months lateforecast Jun 1, 2009

Also in Galway-Cavendish and Harvey

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32583 in the federal list. How to read these figures.