Lake Clear Road Stabilization
Federal contribution
$192,749
Federal share31%
of $630.3K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Township of Bonnechere Valley
- Construction start
- Oct 1, 2009(actual)
- Construction end
- Nov 12, 2010(actual)
Against the original forecast
- Construction start5 weeks lateforecast Aug 28, 2009
- Construction end8 weeks lateforecast Sep 15, 2010
Also in Bonnechere Valley
- Rehabilitation of Fourth Chute Road in Bonnechere Valley$1.1M
- Eganville Community Arena GHG Reduction and Energy Efficiency Upgrades$1.0M
- District 6 - Project 1 and 2 - Snow Country Snowmobile Association - Round Algonquin Park Tour Improvement$162.6K
- Upgrades to the Standpipe Water Storage Tower$104.0K
- Resilient Technology for Disaster Mitigation$80.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32587 in the federal list. How to read these figures.