North West Trunk
Federal contribution
$1.7M
$1,666,665
Federal share33%
of $5.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 5, 2009
201020112012201320142015
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Kawartha Lakes
- Construction start
- Mar 1, 2010(actual)
- Construction end
- Mar 15, 2015(actual)
Against the original forecast
- Construction start10 months earlyforecast Dec 31, 2010
- Construction end2 weeks earlyforecast Mar 31, 2015
Also in Kawartha Lakes