Back to projects

North West Trunk

Kawartha Lakes, Ontario

completeWastewaterISF
Federal contribution
$1.7M
$1,666,665
Federal share33%

of $5.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 5, 2009
201020112012201320142015
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Kawartha Lakes
Construction start
Mar 1, 2010(actual)
Construction end
Mar 15, 2015(actual)

Against the original forecast

  • Construction start10 months earlyforecast Dec 31, 2010
  • Construction end2 weeks earlyforecast Mar 31, 2015

Also in Kawartha Lakes

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32603 in the federal list. How to read these figures.