Southside storm system, Downie Ponds

Stratford, Ontario

completeWastewaterISF
Federal contribution
$2.7M
$2,722,500
Federal share33%

of $8.2M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Stratford
Construction start
Mar 23, 2010(actual)
Construction end
Dec 31, 2010(actual)

Against the original forecast

  • Construction start5 months lateforecast Nov 6, 2009