Malton Community Centre and Library Expansion

Mississauga, Ontario

completeRecreationISF
Federal contribution
$3.3M
$3,333,333
Federal share33%

of $10.0M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedJan 28, 2010
20102011
Built

Approved 8 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Mississauga
Construction start
Sep 2, 2009(actual)
Construction end
Jun 30, 2011(actual)

Against the original forecast

  • Construction start12 months earlyforecast Sep 1, 2010
  • Construction end4 months earlyforecast Oct 31, 2011

Also in Mississauga

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32658 in the federal list. How to read these figures.