Program for the renewal of drinking water and wastewater pipes
Federal contribution
$343,283
Federal share31%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 13, 2009
20102011
Built
Approved 3 months before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Delson
- Construction start
- Jun 9, 2009(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start2 months lateforecast Apr 6, 2009
- Construction end7 months lateforecast Mar 31, 2011
Also in Delson
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32825 in the federal list. How to read these figures.