Reinstallation of Backfill for Embankment Structures on Highway 15
Saint-Bernard-de-Lacolle, Quebec
Federal contribution
$3.6M
$3,575,000
Federal share50%
of $7.2M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedAug 27, 2009
ApprovedJan 26, 2010
2010
Built
Approved 5 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Quebec
- Construction start
- Sep 16, 2009(actual)
- Construction end
- Nov 30, 2010(actual)
Against the original forecast
- Construction start2 weeks lateforecast Sep 1, 2009
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 33120 in the federal list. How to read these figures.