Reinstallation of Backfill for Embankment Structures on Highway 15

Saint-Bernard-de-Lacolle, Quebec

completeHighways and RoadsISF
Federal contribution
$3.6M
$3,575,000
Federal share50%

of $7.2M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedAug 27, 2009
ApprovedJan 26, 2010
2010
Built

Approved 5 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Quebec
Construction start
Sep 16, 2009(actual)
Construction end
Nov 30, 2010(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Sep 1, 2009

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 33120 in the federal list. How to read these figures.