Trans-Canada Prairie Grove Drain Reconstruction

Springfield, Manitoba

completeDrinking WaterISF
Federal contribution
$117,201
Federal share32%

of $370.8K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedSep 11, 2009
ApprovedJan 26, 2010
20102011
Built

Approved 5 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Oct 15, 2009(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start2 months lateforecast Aug 1, 2009

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 33125 in the federal list. How to read these figures.