Seguin Township Beautification and Streetscape

Seguin, Ontario

completeTourismG8LF
Federal contribution
$733,637
Federal share74%

of $985.3K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMay 22, 2009
ApprovedNov 2, 2009
2010
Built

Approved 5 months after the announcement.

Program
G8 Legacy Fund
Construction start
Oct 1, 2009(actual)
Construction end
Mar 31, 2010(actual)

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 33180 in the federal list. How to read these figures.