Tower Road Dam and Reservoir (aka Turtle Creek)
Federal contribution
$9.8M
$9,790,000
Federal share28%
of $34.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 10, 2010
2011201220132014
Built
Approved 9 months before the announcement.
- Program
- Building Canada Fund - Major Infrastructure Component
- Ultimate recipient
- City of Moncton
- Construction start
- Sep 30, 2011(actual)
- Construction end
- May 25, 2014(actual)
Against the original forecast
- Construction end5 weeks earlyforecast Jun 30, 2014