Community Centre Renovations

Sainte-Sabine, Quebec

completeRecreationISF
Federal contribution
$52,846
Federal share32%

of $165.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedAug 27, 2009
ApprovedJan 26, 2010
2010
Built

Approved 5 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
May 19, 2010(actual)
Construction end
Nov 12, 2010(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Apr 1, 2010
  • Construction end5 months earlyforecast Mar 31, 2011