Local Roads Upgrade

Aklavik, Northwest Territories

completeHighways and RoadsISF
Federal contribution
$233,000
Federal share50%

of $466.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 10, 2009
2010
Built

Approved 8 weeks before the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Hamlet of Aklavik
Construction start
Aug 20, 2009(actual)
Construction end
Oct 24, 2010(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Aug 1, 2009
  • Construction end5 months earlyforecast Mar 31, 2011

Also in Aklavik

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 33234 in the federal list. How to read these figures.