Back to projects

Highway 16 Radisson and Maymont

Maymont, Saskatchewan

completeHighways and RoadsISF
Federal contribution
$2.8M
$2,760,800
Federal share50%

of $5.5M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMay 26, 2009
ApprovedJan 27, 2010
2010
Built

Approved 8 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Saskatchewan
Construction start
Jul 13, 2009(actual)
Construction end
May 27, 2010(actual)

Against the original forecast

  • Construction end2 months earlyforecast Jul 31, 2010

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 33296 in the federal list. How to read these figures.