Highway 2 South of Bittern Creek to 5 Kilometres North of Junction Highway 969
Federal contribution
$1.6M
$1,612,983
Federal share46%
of $3.5M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMay 26, 2009
ApprovedJan 27, 2010
2010
Built
Approved 8 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Saskatchewan
- Construction start
- Sep 14, 2009(actual)
- Construction end
- Jul 15, 2010(actual)
Against the original forecast
- Construction start7 months earlyforecast Mar 31, 2010
- Construction end5 weeks earlyforecast Aug 18, 2010
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 33304 in the federal list. How to read these figures.