Highway 32 East of Cabri
Federal contribution
$1.3M
$1,313,325
Federal share50%
of $2.6M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMay 26, 2009
ApprovedJan 27, 2010
2010
Built
Approved 8 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Saskatchewan
- Construction start
- Oct 1, 2009(actual)
- Construction end
- Nov 2, 2009(actual)
Against the original forecast
- Construction start7 months earlyforecast May 1, 2010
- Construction end5 months earlyforecast Mar 31, 2010
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 33332 in the federal list. How to read these figures.