Highway 32 Grid 649 at Lemsford to Prelate from Kilometre 17.67 to 36.63
Federal contribution
$4.5M
$4,500,000
Federal share50%
of $9.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMay 26, 2009
ApprovedJan 27, 2010
2010
Built
Approved 8 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Saskatchewan
- Construction start
- Sep 25, 2009(actual)
- Construction end
- Oct 12, 2010(actual)
Against the original forecast
- Construction start3 months lateforecast Jul 1, 2009
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 33334 in the federal list. How to read these figures.