Bala Falls Road Upgrades
Federal contribution
$361,281
Federal share100%
of $361.3K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 25, 2009
ApprovedOct 23, 2009
2010
Built
Approved 4 months after the announcement.
- Program
- G8 Legacy Fund
- Ultimate recipient
- Corporation of the Township of Muskoka Lakes
- Construction start
- Oct 23, 2009(actual)
- Construction end
- Jun 25, 2010(actual)