Road Improvements
Federal contribution
$100,000
Federal share69%
of $145.8K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 25, 2009
ApprovedOct 26, 2009
Built
Approved 4 months after the announcement.
- Program
- G8 Legacy Fund
- Ultimate recipient
- Township of Perry
- Construction start
- Sep 1, 2009(actual)
- Construction end
- Sep 15, 2009(actual)
Also in Perry