Highway 49 east of Lintlaw to east of Kelvington

Nut Mountain, Saskatchewan

completeHighways and RoadsISF
Federal contribution
$3.1M
$3,094,014
Federal share50%

of $6.2M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMay 26, 2009
ApprovedJan 27, 2010
201020112012
Built

Approved 8 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Saskatchewan
Construction start
Jul 26, 2010(actual)
Construction end
Oct 12, 2012(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Jun 25, 2010
  • Construction end3 weeks earlyforecast Oct 31, 2012

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 33366 in the federal list. How to read these figures.