Highway 6, 6 Kilometres North of Gronlid to South of the North Saskatchewan River
Federal contribution
$700,000
Federal share50%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMay 26, 2009
ApprovedJan 27, 2010
2010
Built
Approved 8 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Saskatchewan
- Construction start
- Jul 22, 2010(actual)
- Construction end
- Nov 10, 2010(actual)
Against the original forecast
- Construction start4 weeks lateforecast Jun 25, 2010
- Construction end2 weeks lateforecast Oct 25, 2010
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 33374 in the federal list. How to read these figures.