Robert Meek Revitalization
Federal contribution
$300,000
Federal share33%
of $900.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 21, 2009
20102011
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Boys and Girls Club of Kingston, Frontenac, Lennox and Addington
- Construction start
- Apr 6, 2010(actual)
- Construction end
- Mar 22, 2011(actual)
Against the original forecast
- Construction start7 months lateforecast Sep 15, 2009
Also in Kingston
- City of Kingston Third Crossing Bridge$60.0M
- Ministry of Transportation Ontario Eastern Region New Ferry Vessels$31.3M
- Kingston Wastewater Treatment Plant Upgrades$25.0M
- Isabel Bader Centre for the Performing Arts at Queen's University at Kingston$15.0M
- Long Range Battery Electric Conventional Transit Buses and Bio- Diesel/Hybrid Buses$12.3M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 33400 in the federal list. How to read these figures.