Back to projects

Wastewater treatment

Saint-Marcel-de-Richelieu, Quebec

completeWastewaterCC
Federal contribution
$1.2M
$1,179,201
Federal share39%

of $3.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 18, 2009
20102011201220132014
Built

Approved 3 months before the announcement.

Program
Building Canada Fund - Communities Component
Construction start
Jun 1, 2013(actual)
Construction end
Sep 30, 2014(actual)

Against the original forecast

  • Construction start2.7 years lateforecast Sep 1, 2010
  • Construction end3 years lateforecast Sep 30, 2011

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 33682 in the federal list. How to read these figures.