Road Construction - Hot Mix Surfacing on Project No. 210, class 4 Municipal Road in the Rural Municipality of Wilton North
Federal contribution
$221,364
Federal share33%
of $680.9K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 29, 2009
ApprovedJan 27, 2010
2010
Built
Approved 7 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Saskatchewan
- Construction start
- Jun 15, 2009(actual)
- Construction end
- Dec 1, 2009(actual)
Also in Wilton No. 472