Road Construction - Hot mix Surfacing on Project No. 102, class 4 Municipal Road, Grid 684 in the Rural Municipality of Eldon No. 471
Federal contribution
$655,910
Federal share30%
of $2.2M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 29, 2009
ApprovedJan 27, 2010
2010
Built
Approved 7 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Saskatchewan
- Construction start
- Jul 18, 2009(actual)
- Construction end
- Dec 30, 2009(actual)
Against the original forecast
- Construction start5 weeks lateforecast Jun 11, 2009
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 33804 in the federal list. How to read these figures.