Road Construction - Hot Mix Surfacing on Project No. 102 and Project 105 on class 4 Municipal Road, grid 684 in the Rural Municipality of Britannia No. 502

Britannia No. 502, Saskatchewan

completeHighways and RoadsISF
Federal contribution
$367,544
Federal share33%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 29, 2009
ApprovedJan 27, 2010
2010
Built

Approved 7 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Saskatchewan
Construction start
Jul 25, 2009(actual)
Construction end
Dec 3, 2009(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Jun 11, 2009
  • Construction end4 weeks earlyforecast Dec 31, 2009

Also in Britannia No. 502

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 33810 in the federal list. How to read these figures.