Restoration of MacLeod Bridge in the Regional Municipality of Invergordon
Invergordon No. 430, Saskatchewan
Federal contribution
$79,893
Federal share21%
of $375.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 24, 2009
ApprovedJan 27, 2010
2010
Built
Approved 4 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Saskatchewan
- Construction start
- Dec 7, 2009(actual)
- Construction end
- Jan 15, 2010(actual)
Against the original forecast
- Construction start6 weeks earlyforecast Jan 18, 2010
- Construction end2 months earlyforecast Mar 31, 2010
Also in Invergordon No. 430
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 33815 in the federal list. How to read these figures.