Renovations to the West Huron Community Centre

Zurich, Ontario

completeOtherISF
Federal contribution
$345,923
Federal share33%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 21, 2009
20102011
Built
Program
Infrastructure Stimulus Fund
Ultimate recipient
Blue Water Rest Home
Construction start
Jan 13, 2010(actual)
Construction end
Oct 28, 2011(actual)

Against the original forecast

  • Construction start2 months lateforecast Nov 2, 2009
  • Construction end2 weeks lateforecast Oct 14, 2011

Also in Zurich

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 34033 in the federal list. How to read these figures.