Road improvements on Highway 389
Federal contribution
$1.1M
$1,050,000
Federal share50%
of $2.1M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 13, 2009
ApprovedJan 26, 2010
20102011
Built
Approved 4 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Quebec
- Construction start
- Jan 27, 2010(actual)
- Construction end
- Jul 8, 2011(actual)
Against the original forecast
- Construction start4 months lateforecast Oct 1, 2009
- Construction end4 weeks lateforecast Jun 7, 2011
Also in Rivière-Aux-Outardes
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 34723 in the federal list. How to read these figures.