Repositioning of Highway 198 along the York River
Federal contribution
$1.2M
$1,238,780
Federal share50%
of $2.5M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 13, 2009
ApprovedJan 26, 2010
20102011
Built
Approved 4 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Quebec
- Construction start
- Jun 28, 2010(actual)
- Construction end
- Mar 31, 2011(actual)
Against the original forecast
- Construction start2 weeks lateforecast Jun 14, 2010
- Construction end5 months lateforecast Nov 1, 2010
Also in Rivière-Saint-Jean
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 34735 in the federal list. How to read these figures.