Swan River Bridge in the Municipality of Livingston
Livingston No. 331, Saskatchewan
Federal contribution
$354,695
Federal share28%
of $1.3M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 29, 2009
ApprovedJan 27, 2010
2010
Built
Approved 7 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Saskatchewan
- Construction start
- Feb 1, 2010(actual)
- Construction end
- Jun 3, 2010(actual)
Against the original forecast
- Construction start2 weeks lateforecast Jan 18, 2010
- Construction end2 months lateforecast Mar 31, 2010
Also in Livingston No. 331
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 34788 in the federal list. How to read these figures.