Grading and Gravelling Highway 513
Federal contribution
$798,097
Federal share20%
of $4.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 12, 2009
201020112012
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Manitoba
- Construction start
- Oct 5, 2010(actual)
- Construction end
- Sep 1, 2012(actual)
Against the original forecast
- Construction end2 months earlyforecast Nov 1, 2012
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 34822 in the federal list. How to read these figures.