Upgrading and Repaving of Route 10 - Southern Shore Highway

Chance Cove Park, Newfoundland and Labrador

completeHighways and RoadsISF
Federal contribution
$761,960
Federal share38%

of $2.0M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMay 11, 2009
ApprovedMay 26, 2009
2010
Built

Approved 2 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Jun 15, 2009(actual)
Construction end
Dec 30, 2009(actual)

Against the original forecast

  • Construction start3 months earlyforecast Sep 20, 2009
  • Construction end4 weeks lateforecast Nov 30, 2009

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 34864 in the federal list. How to read these figures.