Back to projects

Route 935 - Johnson’s Mills Diversion

Johnson's Mills, New Brunswick

completeHighways and RoadsISF
Federal contribution
$810,000
Federal share50%

of $1.6M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 12, 2009
ApprovedJul 28, 2010
2010
Built

Approved 14 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of New Brunswick
Construction start
Aug 5, 2009(actual)
Construction end
Aug 15, 2010(actual)

Against the original forecast

  • Construction end2 weeks earlyforecast Aug 31, 2010

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 34925 in the federal list. How to read these figures.