Route 11 - Grande Anse
Federal contribution
$450,628
Federal share50%
of $901.3K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 12, 2009
ApprovedJul 28, 2010
2010
Built
Approved 14 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of New Brunswick
- Construction start
- Aug 17, 2009(actual)
- Construction end
- Oct 2, 2009(actual)
Against the original forecast
- Construction start2 weeks lateforecast Jul 31, 2009
- Construction end4 weeks earlyforecast Oct 31, 2009
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 34963 in the federal list. How to read these figures.