Water and Sewer Servicing for Whitecourt Airport and Surrounding Subdivisions

Woodlands County, Alberta

completeWastewaterISF
Federal contribution
$1.7M
$1,693,450
Federal share33%

of $5.1M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJul 9, 2009
ApprovedJul 23, 2010
20102011
Built

Approved 12 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
County of Woodlands
Construction start
Aug 12, 2010(actual)
Construction end
Oct 14, 2011(actual)

Against the original forecast

  • Construction end6 weeks lateforecast Aug 31, 2011